Woods: Project eases campus flooding, won’t eliminate it

March 29, 2019

NEW ORLEANS (March 29, 2019) – Three months past the expected completion of the flood mitigation project here at Dillard, 95 percent of the work is done, according to Facilities Director Adonis Woods,...

DU prices emergency generators for all buildings in wake of two-day power outage

Taj Odem March 1, 2019

NEW ORLEANS (March 1, 2019) – Dillard University is pricing new emergency backup power generators for all campus buildings after the latest power outage this academic year, according to Adonis Woods,...

Four more months of drainage work

Four more months of drainage work

India Walton September 7, 2018

India Walton/Courtbouillon Construction workers pause while laying dirt near the Dillard sign today. The campus has four months to go before construction is complete. NEW ORLEANS (September 7, 2018)...

Another milestone: Drainage work moves to Oaks

Another milestone: Drainage work moves to Oaks

Jalynn Lee March 1, 2018

Jamia Collins/Courtbouillon Construction has moved between Williams and Kearney and on to the Avenue of the Oaks. NEW ORLEANS (March 4, 2018) – Another milestone in the 18-month, $6.5 million...